On Tue, Mar 31, 2009 at 4:11 PM, 80n <80n80n at gmail.com> wrote:
> Let me see if I understand correctly what you are saying. You think that
> the currently proposed migration from the old server and old schema to the
> new server with a new schema that includes some referential integrity
> constraints will take longer than the time that has been planned for it?
i think that is what stefan is saying, yes.
> I assume that Matt and co. have done some benchmark tests on the migration
> and have some idea of how long they think it will take.
>
> Matt how long do your benchmark tests suggest the migration will take? How
> much confidence do you have in your test figures?
on the computer i have here (2x quad core opteron, 16Gb ram, 4x1Tb
SATA raid0) the import takes 15h, changeset synthesis takes another
15h and the integrity checks + FK take about 10h, so about 40h in
total. of course, if something goes wrong it doesn't give us much
chance to fix it.
on the new db server we're 3.5h into the import with only 1 table
remaining, so i'm very hopeful that will finish well before 15h.
changeset synthesis and integrity checks should get a similar speedup
from the faster hardware.
i am confident we can do the migration in the 4-day window that we're
committed to, but i can't guarantee anything.
cheers,