> We are installing the Nominatim for plant and it took about 550G disk
> spaces and over 100hours already, we still don’t see any signs to
> complete and we are warrying if our 900G(SATE) disk space is enough.
Yes, it will be enough.
> Now we are running at the message shows:
> Done 43912758 in 529507 @ 82.931458 per second – *Rank 26* ETA
> (seconds):119290
This message seems to say that it has been running for over 6 days on
Rank 26 alone?
Means it will take another ~ 36 hours to complete rank 26, and then (my
rough guess) another week until it has climbed through to rank 30.
> So, we have no idea why it took over 500G already and still not end?
> Does it mean it still import data and the building index still not start?
What you're seeing is the indexing, the last step.
> Core: 1 (this is a mistake we only assign one core, our host is 4) Could
> we pause it by power down the machine and assign 4 Core to it, then
> restart it from the last pause point?
Yes you can interrupt the indexing and then do a
php utils/update.php --index --index-rank 27
to restart indexing from rank 27. Even if you were to restart from rank
26 it would know which elements have been indexed already but
nonetheless I would suggest waiting until rank 26 is complete and then
interrupt.