[OSM-talk] Potlatch & duplicated node

Richard Fairhurst richard at systemeD.net
Thu Aug 28 00:03:00 BST 2008


David Groom wrote:

> Does thtis mean that in theory when creating a "T" junction it would  
> be
> better to start from the existing way, insert a node, and then draw  
> the new
> way "away" from the exisitng way, rather than to start a new way and  
> move
> towards the exiting way and join on to that existing way?

It doesn't really matter as long as the new way doesn't upload until  
the old way has uploaded. I just wait for the ID to turn positive  
before starting a branching way. But I do it with a slightly guilty  
feeling that I should really apply some brainpower to working out how  
to fix this.

cheers
Richard




More information about the talk mailing list