Dear Sam,
It's hard to say when the cut-over date will be for a couple of
reasons. i'm speaking for myself, based on my reading of the
implementation plan[1]. Others are welcome to jump in with their
perspective as well.
Given that the Implementation plan looks like:
Today
- possibly five more weeks of Phase 2
- five or ten weeks of Phase 3
- eight weeks of Phase 4
- Technical work required for cut-over (time period unknown)
- cut over.
So it looks like 18 to 23 weeks, plus some time for the technical
work. So, six months at least, based on the Implementation plan.
Best regards,
Richard